Works Begin on Major Alpha STOPA Investment

The installation of a £600k extension to Alpha’s existing STOPA automated storage system got underway this week. Groundworkers are on site preparing to lay foundations over the Christmas break.

Over the next two weeks, 80 cubic meters (160 tonnes) of concrete will be poured ready for the machine construction to begin in January, with an expected completion date of 30th March

The extension will see a further 10 bays added to the existing 6, increasing storage capacity from 67 pallet spaces to 207. Once complete, the entire system will run 62 meters down the centre of the factory and will be able to house in excess of 600 tonnes of raw material and WIP. Dedicated automated picking carts, strategically located in line with the overall logistics vision for the factory, will allow operators to call on any stored materials and have it delivered to them at the touch of a button. The system will also be integrated into all punch and laser/ punch combination machines, allowing raw sheet metal and part processed items to be delivered via input/ output carts. Once that process is complete, parts will be automatically put back into storage ready for the next process, without any manual handling.

This latest outlay concludes Alpha’s strategic 5-year investment plan, set out in 2015 and is the final step on the journey towards factory automation. The original STOPA system was installed back in 2016 and dramatically improved efficiency through better stock handling and easier inventory management, whilst reducing manual handling and movement of WIP around the shop floor. Since then, 4 automated Kardex shuttle vertical storage systems have also been installed around the factory to further reduce the amount of WIP on the shop floor. The new extension to the STOPA will completely eradicate this with all raw material and parts stored in an automated system. Unlike the original STOPA, which could only store flat sheet metal, the new installation is also capable of storing folded parts.

Managing Director Paul Clews, who has overseen the investment plan since 2015, is delighted with the progress made:

“We’ve achieved everything we set out to do and more, investing close to £4 million in the right technology and this final investment will take us to where we aimed to be in terms of automation and efficiency. We’re not unique in buying the best machinery, a lot of companies also have high spec technology. Where we aim differentiate ourselves is in our operations, through the highest levels of efficiency and productivity. What this system gives us is the ability to Identify, locate and deliver any piece of sheet steel, punched/laser part or folded sub assembly to any given location by the touch of a button. In doing this we will dramatically reduce the amount of waste from our current processes in terms of both movement of people and transportation of parts.”

Once completed in early 2020, Alphas key objective is to achieve total stock/material handling automation. Coupled with the recent introduction of our new group MRP system Sage Enterprise, Alpha aims is to also automate the replenishment of various types of stock, removing the requirement for the manual ordering process on certain lines of stock.

Alpha Say Goodbye to Long-Serving Amada TBZ

Alpha Manufacturing this week bid farewell to their trusty Amada TBZ Panel fold machine after 15 years of service.

The Machine was disassembled and loaded onto several heavy goods transporters, before being transferred to its new home, where it will continue production.

Having been an integral and reliable part of Alpha’s production plant for a decade and a half, the TBZ has folded tens of thousands of parts since its original installation at Alpha. Although still in good working order, technological advances meant that there were more economical and efficient alternatives available in today’s market.

Investment in the cutting-edge Salvagnini P4 Lean panel bender during 2019 meant that it was time for the TBZ to move on. The Salvagnini offers exceptional productivity, with like-for like parts once produced on the TBZ, now being completed in a quarter of the time and to exceptional quality.

Boasting a host of state-of-the-art features and automaton, the Salvagnini is the market leader in sheet metal panel folding and is already proving to be a sound investment. The TBZ now moves on to pastures new and with luck, the new owners will get another 15 years solid production from it.

Salvagnini P4 Begins Part Production in Earnest

Alpha Manufacturing’s latest £1 million machinery investment is now fully operational following a three-month installation and training program.

Purchased as an upgrade to the existing Amada TBZ machine, the P4 Lean Panel Bender takes Alpha’s folding capabilities to another level in terms of productivity, efficiency and flexibility. It also allows Alpha to offer a broader range of product options thanks to its many technologically advanced automated features.

 

The installation comes as part of a major restructuring of the Alpha factory layout which has also seen office staff relocated to a brand new, modern office and welfare facility. The previous office space, located within the factory has been re-purposed and will become a dedicated stainless-steel sheet metal department.

Other machines have been relocated to accommodate the Salvagnini with long term integration of the panel bender into the STOPA storage system in mind. Full factory automation remains the end-goal for Alpha, with the existing STOPA system set to be extended. The Salvagnini machine, along with various others, will then take raw materials and part-processed products form the tower system before returning it to storage once it’s process is complete, ready for the next process.

Shop floor operatives have now completed an intense period of training, provided by Slavagnini, to ensure that the machine is able to run at maximum capacity. With plenty of new work secured already for the machine, the investment is already beginning to pay dividends.

Alpha Manufacturing Announce Latest £1 Million Machinery Investment

Alpha Manufacturing have an announced the latest in a series of manufacturing machinery investments, which will see a brand new £1 million Salvagnini P4 Lean panel folder added to their existing CNC folding department.

This latest investment is a continuation of Alpha’s long-term investment strategy which has seen installations of a STOPA storage system, TruPunch 5000 S12, TruLaser 3030 and Trubend 7000 machine take place over the past 18 months. It also comes shortly after work began to build a brand-new office and canteen facility on their 35-acre Hixon site.

Salvagnini - Alpha Manufacturing

Why Invest in a New Panel Folder?

The P4 Lean will replace the outgoing Amada TBZ panel folding machine which has been in operation for 15 years and will hugely increase Alpha’s sheet metal folding capabilities. A host of additional features and systems have been specified with the P4 to maximise productivity and efficiency, including Salvagnini’s latest interactive programming suite – Streambend, which allows programmers to run a virtual simulation of the part in a 3D environment before any material is processed. Alpha will be one of the first sheet metal fabricators in UK to use this software.

Streambend offline programming software, combined with the P4’s ability to integrate with Solidworks CAD software will dramatically increase Alpha’s panel folding capacity. By moving away from manual shop floor programming to offline office-based programming, Alpha will now be able to offer a much more efficient panel folding service.

Amada TBZ Panel Folder

Key Features of the P4 Lean:

The ABA blankholder automatically changes its configuration and its length according to the dimensions of the panel to bend without any input from an operator.

The CLA tool allows the P4 to make multiple positive and negative short bends to the same part, engaging and disengaging quickly and automatically between the blank and bending blades. This function is ideal for creating upward and downward tabs.

The P tool allows for the handling of very narrow profiles and creating tubular, hidden or radiused bends. It also allows for preformed parts to be folded easily and automatically.

MAC 2.0 (Material Attitude Correction) detects any material variations by the panel bender and, if values are outside the tolerance range, automatically compensates by adjusting the blade movements.

An automated loading/ unloading carriage positions the raw sheet in the machine whilst simultaneously pushing finished parts towards the unload conveyor.

Salvagnini P4 tools

Thanks to Salvanini’s clever automated tools, the p4 is able to fold much more intricate and complex parts, where limitations to the TBZ had previously seen these types of components folded manually on press brake machines. Complex parts with details such multiple positive and negative bends, tabs or embossing have until now been manually re-positioned by an operator for each bend. The P4 however,  enables all of these to be achieved in one seamless process, dramatically reducing processing time and manual handling.

Long Term Plan

As with all of Alpha’s recent investments, the P4 forms part of a long-term factory development plan which will eventually see it integrated into the STOPA storage machine. This will further automate panel folding capabilities as raw material is fed into the P4 and removed once processed without any manual handling.

 “The TBZ machine had served us well but the time came to replace it and as with all of our recent investments, we looked at the bigger picture when choosing a new machine. We don’t just want a like like-for-like replacement but an upgrade which opens up new capacity and opportunities for us whilst also fitting into our overall long-term plan for the business. The P4 ticked a lot of boxes for us in terms of its capabilities and what this allows us to offer our customers.”

Paul Clews – Alpha Manufacturing Operations Director

 

Installation of the Salvagnini P4 is scheduled for early 2019 and will take around 6 weeks to complete. In the meantime, Alpha’s panel bend operatives and programmers will undertake intensive training on the new machine. Programs will be created well in advance of the machine installation so that production on the P4 can begin immediately.